The U.S. Chemical Safety and Hazard Investigation Board (CSB) has completed its investigation into the fatal explosion that occurred on 11 August 2025 at the US Steel Clairton Coke Works in Clairton, Pennsylvania. The Board issued two interim recommendations in December 2025 and released its final report to the public on 10 August 2026. The incident showed once again that facilities handling flammable gas cannot rely on a single measure: procedures, plant layout and equipment safety have to be considered together.

Summary of the incident

According to the CSB, the explosion occurred in the Battery 13/14 transfer area of the plant when coke oven gas was released from process piping and ignited. The CSB describes this gas as highly flammable and toxic.

ItemInformation released by the CSB
Date and location11 August 2025, Clairton (Pennsylvania), Battery 13/14 transfer area
Fatalities2 US Steel employees
Seriously injured4 US Steel employees and 1 contractor employee
Minor injuries6 workers not requiring hospital admission (11 injured in total)
Property damageAn estimated 52.5 million US dollars
FacilityEstablished in 1901, 6 coke batteries with 455 ovens in total

CSB final report: the sequence leading to the explosion

According to the final report, at the time of the incident a double-disc gate isolation valve on the coke oven gas line feeding Battery 13 was being closed and reopened for maintenance. Employees of the contractor MPW Industrial Services were flushing the valve seats with pressurised water. The CSB states that US Steel had been carrying out this practice informally, without a written procedure, for at least three years.

When the two discs of the valve closed, or nearly closed, while water was being applied, an enclosed volume formed between them. The pressurised water filling this volume raised the internal pressure above the limit the valve could withstand. The valve, made of cast iron and more than 70 years old, ruptured; the released gas ignited and exploded within a few minutes. The CSB points out that cast iron is brittle and that safety publications warn against using this material with flammable substances such as coke oven gas. The Board's press release does not state the source that ignited the gas.

The CSB highlights three safety issues:

  • Lack of procedures and hazard analysis: There was no written procedure for flushing with pressurised water, and the procedure for operating the valve did not mention water.
  • Facility siting: Occupied buildings were located directly above the pipe from which the gas was released, less than 20 feet (about 6 metres) above it, and were not designed to withstand an explosion. All of these buildings were heavily damaged.
  • Process safety management: The plant's process safety management system was not effective.

Interim and final recommendations

In its interim recommendations issued on 23 December 2025, the CSB asked US Steel to carry out a comprehensive facility siting assessment for all buildings that are or may be occupied and to mitigate the risks identified in line with recognised industry safety principles. At that time the Board noted that the damaged gas supply piping had been rebuilt in almost the same location and arrangement, that the control rooms were being moved to a building about 100 feet (30 metres) away, and that this location could not be considered safe without a siting assessment. It had also found occupied buildings near hazardous processes at four more coke batteries on the site.

The final report expanded the recommendations:

  • US Steel: Carry out the siting assessment, prepare a written procedure for flushing valve seats with pressurised water, and establish a comprehensive process safety management system for all coke oven gas processes at Clairton.
  • Nippon Steel North America: A corporate process safety governance programme, regular facility audits and prompt correction of the deficiencies found.
  • MPW Industrial Services: Written policies and procedures for cleaning pipes containing flammable or toxic gas, and training for all employees concerned.

Where does ex-proof equipment fit in this picture?

The Clairton report shows that the release resulted from a maintenance practice and an old valve; it does not identify electrical equipment as the cause of the incident. Even so, the incident is a clear reminder that an unexpected release around lines carrying flammable gas is always possible, and at that moment every ignition source in the area matters.

This is why safety in hazardous areas is built up in layers. First, the risk of a release is reduced through procedures, material selection and maintenance management; then the area is classified as Zone 0/1/2, and the electrical equipment used in these zones, such as lighting, junction boxes, control stations and plugs and sockets, is selected from ex-proof products suitable for the gas group and temperature class. In the European Union, the equipment side is governed by Directive 2014/34/EU (ATEX) and the employer's obligations to protect workers by Directive 1999/92/EC; in Turkey, the corresponding regulations are the "Muhtemel Patlayıcı Ortamda Kullanılan Teçhizat ve Koruyucu Sistemler ile İlgili Yönetmelik (2014/34/AB)", which implements Directive 2014/34/EU, and the "Çalışanların Patlayıcı Ortamların Tehlikelerinden Korunması Hakkında Yönetmelik", which implements Directive 1999/92/EC. The Clairton case shows that building siting and procedures are as vital as equipment selection.

The right product with Eksen Mühendislik

When selecting equipment for your hazardous area, the zone, gas group and temperature class need to be assessed together. The “Sahanıza uygun mu?” (Right for your site?) table and the “Ex işaretinin anlamı” (What the Ex marking means) section on our product pages guide you through this matching. You can browse the Ex-Proof Lighting, Control, Distribution and Junction Boxes and Control Stations categories, read our article What is ex-proof? for the basic concepts, or contact us.

Sources